This is our new we just bought on 5 acres of land. It's going to be a ton of work, but we'll have fun doing it. The pace will be slow, but we will get there!

Wednesday, September 28, 2011

Guest bedroom

We officially have a guest bedroom!  Until now, our extra room has been our overflow room.  We finally got things put away and got a bed.  Now we just need to dig our pictures out of storage; the walls are a little bare. Our first offical guests are coming Sunday from Mexico!

Saturday, September 24, 2011

Flooring done!

Other than the two bedrooms that will eventually get carpeting and the laundry room, our flooring is DONE! It was fairly easy to install, just time consuming and made lots of saw dust in the house.  I also finally finished edging out the red wall in the living room.  Furniture is back in place for the most part.  Now all we need is crown molding and baseboards to finish everything off. 
Next on the list...KITCHEN! *Hopefully*, we'll get the cabinets mounted this week and get counters lined up.  We just have to pick them out!

Sunday, September 11, 2011

Updated kitchen photo

Here is the kitchen with the flooring complete.  Next we'll have to install the base sink cabinet, get counters and install everything.  We're hoping to get a new refrigerator during the Black Friday sales in November.  Ours has been having problems keeping a steady temperature.  The freezer will frost up then when it tries to correct itself, it thaws, and leaks a little water on the floor (thus the plastic under the fridge!).  At least the frost/freeze cycle only happens about once a month so we'll just deal with it!  Then maybe over Easter or 4th of July sales, we'll look into matching stove, dishwasher and microwave. 

Thursday, September 8, 2011

9/7/11

The flooring in the kitchen and dining room is officially done!  It's just too messy to take a picture at the moment! Can't wait until we can mount the cabinets and get counters so I can finally unpack.  Too many boxes EVERYWHERE!

Monday, September 5, 2011

New kitchen sink

We picked up our new kitchen sink last night and the faucet and sink base with it.  I decided to do something I wouldn't normally do and got something a little out of the ordinary.  A black composite granite sink.  I'm kind of tired of stainless steel sinks and I hate how white cast iron or acrylic sinks get scratched and marked up. It looks a little marked up but it's just cardboard dust; wipes right off. Next step: picking out countertops!

Sunday, September 4, 2011

We're actually getting somewhere!

After an extended work hiatus, we have kicked it up several gears.  One thing I at least got started, was re-painting our hall bathroom.  We still have another coat to do, hang a new mirror and install a new toilet that we have already purchased.  So once all that's done, I'll take a picture.

Our biggest accomplishment, while yet unfinished, is installing our new floors in the kitchen, dining room, hallway, living room, laundry room and office.  This is what the kitchen looked like before:

And this is what it looked like as of a few days ago (there are actually about 3 more rows completed since this picture.

We then took a break on this room to start on the office (the room on the far end in the picture above).  We wanted to get it up as far as the kitchen was done so we could keep the boards flowing through the doorway. I know, I know...this is extremely sexy carpet, but sorry, it had to go! This is the office yesterday morning:
And this is it as of now. There's a few rows yet to go to get to the doorway but it was going down fairly quickly once we had the carpet, padding, tack strips and staples all out of the subfloor. We had to put mats under our chairs until we pick up some rubber wheels.

Since we had to squish everything from the kitchen into the living room to make room for the flooring process, we were finally able to put some of it back, somewhat in place.  Justin spent time fashoning two cabinets into a sink base with the old sink, but we've decided to spend the extra money and buy an actual sink base, new sink and faucet.  Then there's no question of the sink not fitting quite right or holding the weight of all the water since these aren't true kitchen cabinets. 

My injury du jour was cutting my hand while removing the old bathroom mirror that was securly fastened to the wall with doubleside foam tape crap.  I was pulling a LITTLE harder than I thought! I held a rag on it but it wouldn't stop bleeding.  I was hoping I wouldn't need stitches as there was nothing to stitch it to!  So Justin says "put some toilet paper on it"! Yes, I know guys can do this for small nicks on their face while shaving, but this was a little more severe.  Finally, it did stop bleeding bleeding but the 4 or 6 layers of TP was then fused to my wound.  Oh well.  It's healed about 90% now.  Just another lesson in the need to be patient! :)

Since there are a couple Labor Day sales going on, I think the plan is to go pick up the sink base cabinet, the sink, faucet and assessories later today.  Then once the floor is done completely in the kitchen, we can get kitchen counters and siding for the front of our house.  Big steps!


Saturday, August 20, 2011

Back to work!

So, it's been about a month and a half since we've done ANYTHING at this house!  After busting our butts to get moved in, we took a break.  Justin's mom is coming to NC the beginning of October, so we're using that as incentive to get back in gear. 

Monday, Justin went and picked up all the flooring for the living room, dining room, kitchen, hallway, office and laundry room...all 48 boxes. Our poor truck was soooo weighed down!


While he was gone, I finished painting the parts of the kitchen where we most recently replaced sheetrock. Simple enough job, we just put it off with everything else. (I know our kitchen walls still look pretty rough but we planned this. For now, we have appliances and cabinets sufficient enough to have a basic kitchen. We will evenutally be remodeling the whole thing and the walls will have something coving them up: wainscoting, stonework, something. It was either that, or replacing all the sheetrock, so we just did a rough patch up job and painted it so it didn't look too horrible.)

After we had all the floors cleared to bring in the boxes of flooring, Romulus got a whiff of something and decided to gnaw on the subfloor.  Ahhh, just something else to add to the list. The very bottom of it goes all the way through! Hope it tasted good!

We hoped to put our floor in this week as we had time, but we've been working on our new Kingdom Hall in the masonry department and it's been kicking our butts.  I've only done it part of one day, so I know Justin's wore out since he's there all week!  So hopefully we'll get it done in the next week or two.  Then we can finally install the kitchen cabinets, build some counters, and have a kitchen sink!  I'm tired of doing the dishes in a kiddie pool on the front porch. :)